Firmus, backed by Nvidia, cancels IPO; AI data center funding faces a downturn.

Firmus, backed by Nvidia, cancels IPO; AI data center funding faces a downturn.

Australian data center operator Firmus Grid has withdrawn its plans to list on the Australian Securities Exchange (ASX) after facing a lukewarm reception from investors in the public market, opting instead to seek private financing. This marks the second major data center IPO to fail in three weeks, highlighting the serious challenge facing the market in pricing AI infrastructure assets in the public market.

Firmus originally planned to raise up to US$5.5 billion, priced at A$11 per share, corresponding to a valuation of approximately A$43.7 billion (US$30.4 billion). According to Bloomberg, by the subscription deadline, no clear pricing or transaction structure had appeared in the book. Firmus initially lowered its offering price to A$8, about 25% below the offering range, and attempted to hold the floor at A$8.25.

Ultimately, the company announced on Friday that it was withdrawing its listing application, citing "recent market volatility and current market conditions" as the reason, stating that "the terms of the transaction do not adequately reflect the company's business strength and long-term growth prospects," and indicating that it would turn to the private market for funding.

This setback directly impacted related parties. Shares of Maas Group, one of Firmus' shareholders, plummeted by as much as 30% during trading, marking its largest single-day drop in history.

Valuation jumps sixfold in six months: from $5.5 billion to $30.4 billion

Firmus started with Bitcoin mining in 2019. In February of this year, it secured $10 billion in debt financing led by Blackstone and Coatue. In April, Coatue led a funding round that valued the company at $5.5 billion. In August, a $2 billion funding round involving Nvidia, Coatue, Blackstone, and Jane Street raised the valuation to $10.5 billion. Less than two months later, the IPO required public market investors to enter at a valuation three times the August funding price.

In contrast to this valuation, according to Breakingviews, Firmus currently has only 42 megawatts of installed capacity out of approximately 1 gigawatt of pipeline, representing about 4%. The company has recently shifted its business focus from Australia to Malaysia and Indonesia, aiming to serve hyperscale cloud computing clients such as OpenAI and Meta.

According to the draft prospectus, the company reported a net loss of $77 million in the first half of FY27 and did not provide any earnings forecasts beyond June 2027.

Australian institutional investors reacted coldly:

  • Morningstar analyst Lochlan Halloway pointed out that this IPO has "boom-era" characteristics, and believes that the "sharp increase" in valuation in the short term is alarming.
  • Merlon's Kirit Hara stated that their investment process "does not allow us to buy hope and dreams."
  • Katana's Romano Sala Tenna admitted, "We're having trouble with fundamental arithmetic."
  • Joseph Koh of Blackwattle declined to participate in the subscription, citing "too many unknowns."

Alternative valuation tools failed to convince institutions.

When traditional financial metrics failed to support pricing, Firmus' underwriters switched to a new valuation framework called "EV+1/EBIT+2". According to Antony Currie of Breakingviews, this metric calculates enterprise value by dividing the company's net debt 12 months from now by the expected earnings before interest and taxes (EBIT) two years from now.

The underlying logic is that data center developers typically cover up to 90% of construction costs with debt and can start generating revenue within about a year, so current financial figures are difficult to fully represent.

However, critics point out that the metric is highly susceptible to manipulation—capital expenditure assumptions can be inflated to boost corporate value, and any delays in the supply of licenses, equipment, electricity, or water can turn "EV+1" into "+2" or "+3," with EBIT realization being postponed accordingly.

According to reports, Oracle's 1.3 gigawatt "Lighthouse" campus project has been delayed this week, and Project Jupiter has also declared force majeure, indicating that "+1" is merely an optimistic scenario.

At the same time, the IPO structure itself has raised concerns among investors. Approximately half of the IPO shares were allocated to "specific existing strategic and financial investors," including Nvidia, Coatue, Blackstone, and Jane Street; existing shareholders can sell up to 20% of their holdings from the first day of listing.

Supply pressures coupled with pricing controversies have made potential investors more hesitant. Furthermore, the IPO proceeds will primarily be used to purchase Nvidia GPUs to support Firmus's first project in Batam, Indonesia—a circular structure where Nvidia invests in Firmus, and Firmus then uses the raised funds to reinvest in Nvidia's chip purchases—has raised additional questions in the market.

Equity valued below debt: From growth stocks to credit stories

What alarms the market most is Firmus's balance sheet structure.

According to Morningstar estimates, Firmus' debt is approximately $30 billion, about six times its own profit forecast. At its IPO price of AUD 11, its equity market capitalization was approximately $30.4 billion, with debt roughly equal to equity. However, if the price remained at AUD 8.25, the equity value would shrink to approximately $23 billion, about $7 billion less than its debt. If the price fell to AUD 8, the gap would widen further.

In other words, at the price level that the underwriters were trying to maintain, Firmus's equity was already below the company's total debt before the first day of trading. This means that the stock was essentially a "highly leveraged credit instrument with a ticker symbol."

Coupled with the U.S. 10-year Treasury yield climbing to a 24-year high of 5.36% this week, Goldman Sachs stated that the cost of capital for $30 billion in data center debt is only going in one direction.

Narrowing Window: Data Center IPO Queues Face Challenges

Firmus is the second mega-data center IPO to falter in three weeks. This follows SoftBank's SB Energy's IPO roadshow being suspended in late September due to additional inquiries from the SEC and investor concerns about its approximately $60 billion valuation and heavy reliance on a single OpenAI customer.

There are still many data center projects queuing up for IPOs: Singapore's DayOne—which happens to be Firmus' partner in Batam—plans to raise up to $5 billion in the US as early as November at a valuation of $20 billion; Switch has filed a confidential IPO application; Vantage and CyrusOne are evaluating IPO options; and Nscale in the UK has just completed a $3.36 billion pre-IPO convertible bond financing.

According to Ke Yan of Shenton Research, speaking to Reuters, "The dividing line is whether the demand has been contracted and implemented, whether the power supply is in place, or whether it is still just in the planning stage." Firmus, with its 42 MW actual installed capacity corresponding to a 1 GW pipeline, is clearly on the "planning stage" side.

From a macro investor behavior perspective, according to a Goldman Sachs Asia sales desk report, hedge funds have increased their allocation to the technology sector due to macroeconomic uncertainties. Mag7's net exposure accounts for about 22% of Goldman Sachs' prime brokerage account's total US equity exposure, the highest since the beginning of 2022.

Goldman Sachs GS Research estimates that global AI investment will exceed $1 trillion this year, with the US and Asia combined contributing over 80% of the net increase in data centers. Funding is not scarce, but the market's orientation is clear: investors are still betting on AI, but prefer to make their exposure through large technology companies with sound balance sheets and the ability to independently absorb large-scale capital expenditures, rather than through highly leveraged, low-revenue project-based companies whose main selling point is "pipeline planning."

Risk Warning and DisclaimerInvesting involves risk; please exercise caution. This article does not constitute personal investment advice and does not take into account the specific investment objectives, financial situation, or needs of individual users. Users should consider whether any opinions, views, or conclusions in this article are suitable for their specific circumstances. Any investment decisions made based on this information are at your own risk.