US opposition intensifies! Another giant Oracle data center may be stalled due to power outage.

US opposition intensifies! Another giant Oracle data center may be stalled due to power outage.

Oracle's data center construction crisis continues to spread. Following the declaration of force majeure for the Jupiter project in New Mexico, the 1.3GW mega-data center "Project Lighthouse" in Wisconsin is facing another crisis—not due to site selection or funding, but because of a power outage.

According to a recent report by data center research firm Aterio, the power supply approval process for the Lighthouse project has been restarted by the Wisconsin Public Service Commission (PSC), putting the statutory review process back on track. This means that Oracle's previous promise of "delivery to customers in the second half of 2027" is highly unlikely to be fulfilled. In the baseline scenario, full-power operation will be delayed until October 2028, and in a pessimistic scenario, it will be delayed until the spring of 2029. Following this news, Oracle's stock price fell 1.8% that day, and the company has not issued a public response.

This is the second project among Oracle's five core data center campuses to be explicitly marked as having a delay risk. Just two weeks ago, Barclays credit strategist Andrew Keches told clients that the New Mexico issue "had no cascading impact on other projects"—but reality is gradually proving that assessment wrong.

Approval restarted: More than 500 documents, starting from scratch.

The Lighthouse project, located in Port Washington, Wisconsin, was developed by Vantage Data Centers with Oracle as a tenant. It is part of the OpenAI Stargate construction plan and has a total power demand of 1.3GW and a critical IT load of approximately 902MW.

The project's power bottleneck lies in the fact that the park's power supply relies on a new high-voltage transmission line built by American Transmission Corporation (ATC), and ATC must obtain approval from the PSC before it can begin construction.

The process had reached a critical stage. ATC's application was deemed a "complete application" in December 2025, but the company subsequently supplemented or resubmitted 564 documents, adding route proposals and temporary bypass routes. On August 7th of this year, the PSC committee unanimously revoked the original "completeness determination"—reportedly the first time in the committee's decades-long history, and possibly the first time ever.

PSC Chair Summer Strand stated, "The scale and number of change requests... have created obstacles to participation from all parties and the public." Commissioner Marcus Hawkins put it more directly: "We have a strict timetable, but only if the applications are complete."

The administrative law judge subsequently determined that ATC had failed to comply with the order to specify the changes, and the PSC closed the case on September 10 without making a substantive ruling. ATC resubmitted the application on September 18, and the statutory review clock was reset to zero.

ATC was initially planned to begin construction in December 2026 and be completed by the end of 2027, aligning with Oracle's delivery schedule. This plan has now officially fallen through.

Timeline: Earliest 2028, most likely 2029

Under Wisconsin law, the PSC must make a determination on the completeness of the application within 30 days (the next deadline is October 19), followed by 180 days to make a substantive decision, with a possible extension of 180 days. After that, construction can only begin with 6 months' notice.

Based on this, Aterio deduced three scenarios:

Optimistic scenario (low probability): Partial power supply achieved in October 2027, and full power supply of 1.3GW achieved in August 2028;Baseline scenario: Partial power supply achieved in December 2027, full power supply achieved in October 2028, with effective load ramping starting in the first quarter of 2028;Delayed scenario: Partial power supply to be achieved in June 2028, and full power supply to be achieved in April 2029.

Aterio points out that, historically, the PSC has initiated extended reviews in all similar large-scale transmission cases it has examined. For the 345kV project, the actual time from completion of the assessment to the decision was 355 to 358 days, not the theoretical 180 days. In other words, the extended review scenario is the historically grounded benchmark.

"Construction at Port Washington is progressing steadily, but power supply depends on a regulatory process that has been restarted," said Javier Reyes, research director for Aterio's data center. "Two buildings in the park have been topped out, but there is no grid connection, so the chips inside will have nowhere to plug in their power."

Bill: Costs have jumped 75%, and debt pressure continues to accumulate.

In addition to the timeline, project costs have also ballooned. The ATC's resubmitted estimate for the "Ozaukee County Distribution Interconnection Project" has risen to $2.48 billion to $2.72 billion, approximately 75% higher than the original application of $1.3 billion to $1.7 billion, potentially making it the most expensive single transmission project in Wisconsin history. Of this, approximately $1.1 billion is earmarked for the Decker Grid Stabilization System (E-STATCOM), a portion of which Oracle has committed to cover.

Tom Content of the Citizens Utility Board cited data indicating that Wisconsin's largest electricity customer currently consumes less than 100 megawatts, while the campus's peak electricity consumption could reach as high as 3,500 megawatts.

Financing pressures are equally significant. According to Barclays data, the Wisconsin campus's construction funding came from $15 billion of a $38 billion loan package from Vantage, which reportedly faced difficulties in syndicated sales. Furthermore, due to tariff requirements for Wisconsin's large electricity customers requiring applicants to have a credit rating of at least A-, while Oracle's current rating is BBB-, the company will face margin call pressure—Oracle itself disclosed that related letter of credit guarantees could exceed $100 million annually, with total guarantees reportedly exceeding $7 billion. All of this points to a campus that may not be fully powered until 2029.

In a research report the day after New Mexico declared force majeure, Goldman Sachs TMT analyst Sean Johnstone warned that "permit approvals, power redesign, community opposition, and local infrastructure constraints are threatening construction schedules and financing assumptions." The situation in Wisconsin, however, is just one of these factors alone that has already had a substantial impact.

The cost of delays: Nearly 100 billion yuan in monthly revenue is postponed.

Goldman Sachs equity research estimates that hyperscale cloud service providers need approximately $11.6 billion in AI revenue annually per GW of computing power to achieve a 15% ROI on AI computing power spending in 2026-2027. Based on Lighthouse's approximately 0.9GW of IT capacity, each month's delay corresponds to a revenue deferral of approximately $850 million to $900 million. Bloom Energy stated in its Q2 earnings call that for a 1GW data center, powering it up a month earlier could generate approximately $1 billion to $2 billion in revenue value.

Meanwhile, the pressure on capital expenditures has not eased due to the delay. Oracle's "must-fulfill" lease for the Jupiter project means that the company will still bear the holding costs even if the park fails to go live. Barclays points out that hardware capital expenditures are typically paid two to three months before the asset goes live; what is being delayed is revenue, not costs. Oracle's FY27 capital expenditure guidance is as high as $95 billion, far exceeding the $55.7 billion in FY26, further compressing its financial flexibility.

This predicament is not unique to Oracle. According to Goldman Sachs' latest "Carbon Economics" report, the scale of new high-voltage transmission lines built in the United States has shrunk dramatically from an average of 1,700 miles per year between 2010 and 2014 to 350 miles between 2020 and 2023, with the median time from grid connection application to commercial operation approaching five years. Engine manufacturer INNIO told Goldman Sachs that the grid connection cycle has lengthened from about two years historically to more than seven years today.

Port Washington is a microcosm of this statistic: 1.3 GW of electricity demand awaiting new high-voltage lines, up to five new substations, and a regulator that has lost patience. This is also the backdrop against which Goldman Sachs predicts that by 2030, 28% of the electricity demand for U.S. data centers will be supplied by off-meter natural gas and fuel cells—while by 2025 this proportion is "virtually zero."

Crisis Transmission: From "Isolated Incidents" to Systemic Concerns

In a brief statement following the declaration of force majeure on its New Mexico project, Barclays' Andrew Keches asserted: "The headlines are big, but the actual impact is minimal... There is no ripple effect on other projects, and credit should not be affected."

However, the reality is that Oracle's credit default swaps (CDS) surged to a record 237 basis points the following day, and the "no transmission" assessment has become increasingly fragile as the Wisconsin project came to light.

It is worth noting that the reasons for delays in Oracle's various projects differ: New Mexico is embroiled in pipeline and air permit issues, while Wisconsin faces obstacles in grid regulatory approvals. As Aterio points out, when each project has its own "unique reason for delay," the logic of "isolation" no longer holds true.

Barclays considers the Saline project in Michigan, which is considered relatively safe and has reportedly secured power supply and permits, "one of the most de-risked assets in Oracle Pipeline," with initial deliveries expected by the end of the year, less than three months away. As the original text states, historical experience shows that the next one to run into trouble is often the one considered the safest.

As Goldman Sachs' Johnstone put it, "This is a reminder for lenders and data center investors that third-party-developed AI infrastructure isn't always as stable and reliable as it seems." The construction boom, backed by hundreds of billions of dollars in debt, was logically predicated on the assets going live on schedule. In reality, however, they haven't.

Risk warning and disclaimerInvesting involves risk; please exercise caution. This article does not constitute personal investment advice and does not take into account the specific investment objectives, financial situation, or needs of individual users. Users should consider whether any opinions, views, or conclusions in this article are suitable for their specific circumstances. Any investment decisions made based on this information are at your own risk.